63.9 F
Reno

PHOTOS: Day-Long Celebration Planned for Bridge Opening Next Week

Date:

Virginia Street Bridge. Photo by Dana Nollsch.
Virginia Street Bridge. Photo by Dana Nollsch.

By Carla O’Day | Photos by Dana Nollsch

The Virginia Street Bridge is nearing completion and scheduled to open next week for the first time since closing for construction last summer.

A ribbon cutting ceremony with local dignitaries is planned at the new bridge, corner of First and Virginia streets by the Truckee River, at 11 a.m. April 12.

The 185-foot-long bridge will be open mostly to pedestrians that day but open permanently to motorists late that evening. City Plaza on the northeast side of the bridge is also re-opening.

Performances by the Reno Wind Symphony, vehicles from the National Automobile Museum, a Tesla car and mule team are among those taking part in the procession over the bridge. The mules, Jyp and Jude, are owned by Ralph Atkinson of Reno.

“Someone wanted a team and a wagon, and my name came up,” Atkinson said. “Back in 1905, the first thing that probably crossed the bridge was a mule and a wagon.”

The 110-year-old bridge was an impediment to flood conveyance in recent years, and its poor condition became a safety problem. The new bridge’s replacement structure eliminates the center pier, bettering flood capacity and reducing potential for debris to hang up during high water, said Kerrie Koski, city public works street program manager.

“The design life on this one is well beyond 100 years,” Koski said. “It’s hard to put a number on it.”

Studies showed at least 14,000 motorists used the former bridge daily, along with pedestrians.

Area contractor Q&D Construction built the bridge and worked closely with area businesses affected by the road closures. For example, Koski said signs were placed directing people to nearby businesses.

“We had a lot of participant engagement from all the businesses and it was important to the businesses that it wasn’t just a sea or orange cones,” Koski said. “It helped to have a local contractor.”

The bridge’s two arches were one of the biggest construction challenges. Weighing 400 tons each, workers put them together on dry land on the south side of the river. Once complete, they were inched across the river with 100-ton jacks, moving at about 4 feet per hour for four days.

“We enjoyed the complexity and the challenges and the overall goal,” said Jeff Bean, Q&D heavy/civil department vice president.

Despite all the newness, the historic lighting structures and rails were refurbished and reinstalled in the area. Old plaques were also reinstalled. Additionally, an interpretive area with panels that point out the former bridges’ structures and the importance of flood walls is located on the bridge’s southeast corner.

Topographic art depicting the region is now in the river access area, along with access to the river from City Plaza.

The $18.3 million project began in June 2015 and finished about a month ahead of schedule.

Funding came from local, state and federal agencies, such as the Federal Highway Administration, U.S. Army Corps of Engineers, Nevada Department of Transportation and Truckee River Flood Management Authority.

Carla O'Day
Carla O'Day
Carla has an undergraduate degree in journalism and more than 10 years experience as a daily newspaper reporter. She grew up in Jacksonville, Fla., moved to the Reno area in 2002 and wrote for the Reno Gazette-Journal for 8 years, covering a variety of topics. Prior to that, she covered local government in Fort Pierce, Fla.

TRENDING

RENO EVENTS

MORE RENO NEWS